Extension Granted

SnoExtension FromExtension Upto
1 30-09-2019 31-03-2020
2 31-03-2020 31-12-2020
3 31-12-2020 30-06-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)
4 30-06-2021 29-12-2021

Project Location

Promoter Detail

HEBE INFRASTRUCTURE PRIVATE LIMITED (MAHAGUN GROU